The completion date for the $50-million County Road 43 construction project has been extended by a couple of months.
United Counties of Leeds and Grenville Construction Manager Bill Guy says most of the work on the project this year has concentrated on the east side of Kemptville Creek.
Work has included constructing roundabouts and upgrading related infrastructure.
It’s also included the removal and replacement of the two-lane bridge on County Road 43 over the Kemptville Creek with a new four-lane bridge extending to the south.
Guy says one lane will be open in both directions over the bridge during the winter and, R.W. Tomlinson, the company overseeing the project, will break from Dec. 18 to mid-January when they will continue with work under the bridge.
He tells the Vista Radio Newsroom that it’s expected the work over the winter months will mean a completion date by the end of July.
“If we don’t take advantage of the winter months then it may extend the project into next fall. We don’t want to do that and Tomlinson doesn’t want to do that.”
Guy adds there are three lifts of asphalt involved in the project and he says the two base course layers are in place.
He says the third lift, the top course, will be completed in the spring for the entire job.